Scope of Work
South Effluent Pumping Station Upgrades:
Removal of the ground level floor of the existing building, and provision of new, larger ground level structure tied into the lower levels of the existing structure. New ground floor structure includes entrance vestibule, retrofitted existing access stair to levels below, an electrical room, sampling room, and lower floors equipment access/lifting area.
New Cast in Place Concrete Walls and roof slab.
Provision of monorail hoisting system to lift equipment from the intermediate level and basement.
New Architectural brick masonry.
Provision of new asphalt driveway, concrete sidewalk and grading.
Provision of new automatic effluent water strainers, piping, valves, fittings accessories, and associated controls and wiring
Provision of new sampling room
Removal and replacement of effluent sampling pumps
Provision of new electrical room, removal and replacement of MCCs, UPS, RPU panels
Construction of new south access road to reach the South effluent pumping station including landscaping upgrades